15. The minimum cost of work that the holder of a claim must carry out on the land that is subject thereto, pursuant to section 72 of the Act, shall be determined in the following tables and varies according to the area of land that is subject thereto, according to the number of terms of the claim and depending on whether the land is located in one of the following areas:(1) north of the 52nd degree of latitude:
Area of land subject to a claim
Number of _______________________________________________________________
terms
of the
claim Less than 25 ha 25 to 45 ha More than 45 ha
1 $48 $120 $135
2 $160 $400 $450
3 $320 $800 $900
4 $480 $1,200 $1,350
5 $640 $1,600 $1,800
6 $750 $1,800 $1,800
7 and more $1,000 $2,500 $2,500
(2) south of the 52nd degree of latitude:
Area of land subject to a claim
Number of _______________________________________________________________
terms
of the
claim Less than 25 ha 25 to 100 ha More than 100 ha
1 $500 $1,200 $1,800
2 $500 $1,200 $1,800
3 $500 $1,200 $1,800
4 $750 $1,800 $2,700
5 $750 $1,800 $2,700
6 $750 $1,800 $2,700
7 and more $1,000 $2,500 $3,600